Camp Nazareth Cabin Expansion Project Days 7-16 (11/4/15)

The Camp Nazareth Cabins are undergoing a major upgrade with this expansion. New bathrooms, showers, a large common room, covered front porches, and climate control (hvac) are just some of the planned upgrades.

The project is scheduled to be completed by March 1, 2016.

Photos show scenes from days 7-16 of construction: Oct 27- Nov 4, 2015


View Additional Project Photos
Oct 27: Pouring the first footer (for cabins 7 & 8). More to come...
Oct 27: Rain prevented the Mixer from getting all the way to cabins 7 & 8, but nothing that a bucket can't take care of.
Oct 27: The footer has to be the right depth and thickness, and it has to be smoothed out.
Oct 27: It takes a lot of concrete for each footer. Here cabins 7 & 8 get theirs poured.
Oct 28: Instead of a foundation, we decided to put in moats around each cabin in case of attack. Camp Nazareth's own version of Forge of Empires
Oct 29: This was a little "game" called "fjord the foundation". Get the digger over the trench without it falling in. He was successful.
Oct 29: You have to get it right before you lay the foundation.
Oct 30: Some block cutting is required.
Oct 30: Cabins 7 & 8 getting their foundation
Oct 30: While the foundation of cabins 4 & 5 were being laid, cabins 1 & 2 were being dug and prepped.
Oct 30: Block + Mortar + Work = Foundation
Oct 30: Working on the foundation of Cabins 4 & 5
Oct 30: Completed foundation of Cabins 7 & 8
Nov 2: Beginning the digging for Cabins A & B
Nov 2: Nearly complete foundation of Cabins 4 & 5
Nov 4: The foundation completed at 7 & 8.
Nov 4: Digging begins at Cabin 3.
Nov 4 : A view of Cabins A & B. The horizontal pieces show the level of the finished floor.
Nov 4: Digging the plumbing from Cabins 7 & 8 to the Bathhouse extension
Nov 4: Plumbers at Cabins 7 & 8
Nov 4: Waiting for this concrete to pour you could exercise your patience
Nov 4: Concrete for the footer of Cabins A & B being poured
Nov 4: The footer was a stiffer pour so a little harder to work with
Nov 4: Getting the footer ready for Cabins A & B